What happens to costs which were not approved to be eligible within the CFS? Is it possible to use that budget in later years?

Recent Comments



    The budget breakdown in the Specific Agreement Annex II, table 2 is an indicative breakdown of costs. The partners are allowed to adjust the estimated budget between themselves and between the different budget categories, without this adjustment being considered as an amendment of the Specific agreement. This includes also a transfer of budget between the years. If costs are not considered eligible during an Interim Payment Claim the max. grant will not be automatically reduced.