2016_159_AF6

DLS Implementation Project - Path 2

Timeline

2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
Mar. '17CompletedDec. '20

Implementing Partners

ENAV
Leader: ENAV
Lufthansa Group
Contributor: Lufthansa Group
DFS
Contributor: DFS
TAP Portugal
Contributor: TAP Portugal
Ryanair
Contributor: Ryanair
Bulatsa
Contributor: Bulatsa
DSNA
Contributor: DSNA
Croatia Control
Contributor: Croatia Control
MATS
Contributor: MATS
Hungarocontrol
Contributor: Hungarocontrol
Pansa
Contributor: Pansa
ESSP
Contributor: ESSP
LPS
Contributor: LPS
Fintraffic ANS
Contributor: Fintraffic ANS
LFV
Contributor: LFV
EANS
Contributor: EANS
NAV Portugal
Contributor: NAV Portugal
Arinc
Contributor: Arinc
DCAC
Contributor: DCAC
Oro Navigacija
Contributor: Oro Navigacija
ENAIRE
Contributor: ENAIRE
NATS
Contributor: NATS
Sita
Contributor: Sita
LGS
Contributor: LGS
Austrocontrol
Contributor: Austrocontrol

Description

The Path 2 project is currently ongoing under the coordination of SESAR Deployment Manager. It is a multi-stakeholder project with the participation of the ANSP (ENAV, ANS Finland; Croatia Control; DCAC; Lufthansa; DFS; ENAIRE; ESSP; HungaroControl; LGS; EANS; LPS SR; LFV; MATS; NATS; NAV Portugal; Austrocontrol; PANSA; BULATSA; Oro Navigacija; DNSA) Airlines (Ryanair and TAP) and the industry (Arinc and SITA).

In October 2016, the European Commission mandated the SESAR Deployment Manager to assume the role of DLS implementation project manager responsible for organizing, implementing and monitoring the activities identified in the DLS recovery plan. The DLS Recovery Plan aims to set a realistic path, identifying the relevant actors, milestones and next activities needed to be undertaken in order to achieve the full DLS implementation in Europe allowing Initial Trajectory Information Sharing functionality by the deadlines set in the Pilot Common Project.

As part of this Recovery plan two implementation projects were defined:

The 2015_161_AF6 Path I – Implementation of the DLS transitional solution, led by ENAIRE. This multi-stakeholder project, completed in December 2018, focused on the Multi-Frequency implementation and on the deployment of Best-in-Class avionics (both ELSA’s recommendations) permitting to meet the EU (IR) 310/2015, with a deadline set in February 2018.

The Implementation Project 2016_159_AF6 DLS Implementation Project - Path 2 aims to identify the next steps towards the target solution, in order to continue to grant the required level of performance and the achievement of full AF6 implementation, fixing all technical and non-technical open points.

A third Project, to perform activities strictly correlated with the Path 2 project, enhancing the scope of works and developing further technical and non-technical solutions for DLS provision, was awarded.

The 2017_089_AF6 - IP1 - DLS European Target Solution assessment aimed to design of a Common ATN Backbone at European Level, as a first step towards the target solution, and at the same time, the performing of a detailed analysis on the technical and non-technical elements needed to ensure a full DLS implementation in Europe, based on previous technical studies and on the inputs stemming from the Capacity Assessment. This project was completed on December 2019.

At the project completion the following objectives will be achieved:

  • The European DLS Common Governance will be defined;

  • The Service Areas will be identified;

  • The system architecture will be defined;

  • The Business Case study for the Target Solution will be elaborated;

  • The Services to be provided by the Model D will be analysed;

  • The improvements on legacies DL infrastructures will be identified;

  • PENS to connect G/G (BIS) routers will be used;

  • IoP improvements of the ATN DL Networks operated by different entities.

Disclaimer

A certain number of completed projects are highlighted as it was already possible to provide detailed information on specific benefits brought by these projects. In time, SESAR Deployment Manager will provide such detailed information for every completed project.

Additional Information

  • Project Type: Air Navigation Service Provider
  • CEF Call Year: 2016
  • Civil/Military: Civil
  • Multistakeholder: Yes
  • Main AF: AF6 - Initial trajectory information sharing
  • Sub AF: S-AF 6.1 - Initial Trajectory Information Sharing
  • Progress Percentage: 100%

News & Events

6a0e2b46-ab14-49c8-a054-53b056fe57b2 reworked without ECTL LOGO
Featured News
‘CLEAN ATM 2’ & ‘GREEN CNS’ awarded €141 million to accelerate modernisation of European sky
12.11.2024Read more
Homepage Hero May 2024
Featured News
Funding opportunities for SESAR deployment ATM modernization projects!
24.09.2024Read more
events-april-2024 1600x500-min
Featured Event
STAR Training on CEF 2 Monitoring Windows and Reporting
09.01.2025Read more
events-april-2024 1600x500-min
Event
25th ICNS Conference comes to Europe!
08.04.2025Read more
events-april-2024 448x298
Event
2025 Interim Payment Webinar
11.12.2024Read more
2-9900000000079e3c
Event
A Decade of Transformation: Modernising European Air Traffic Management As One
04.12.2024Read more
events-april-2024 448x298
Event
STAR Training for Implementing Partners 2024
29.11.2024Read more
events-april-2024 1600x500-min
Event
Annual Meeting and 2023 CEF2 Transport Call Kick Off Meeting
28.11.2024Read more

Subscribe now

Please complete and submit the form below to be subscribed to ‘News and views from the SESAR Deployment Manager’.
You will receive a verification email before you are added to our subscriber list.