It is important to distinguish two different cases in the postponement of the monitoring milestones
– Case 1. The postponement of the monitoring milestones does not cause a delay of the IP overall delivery (no changes in the end date of the project), and has no impact in the milestones reported at Action level. In this case the amendment is not expected.
– Case 2. The postponement of the monitoring milestones has an impact on the Monitoring milestones at Action level. In this case an amendment is needed
In any case the postponement / delay has to be communicated in the monitoring exercise.