Where we have multiple PCP deployment technical projects, can there be one submission of parts A, B and C with separate parts D for technical aspects?

2.55K viewsPrevious INEA CEF Calls (2014 and 2015)

A: Part A, B, C and D shall always compose a single application.

However, in case an organisation submits to the SDM a number of single PCP deployment projects, presented through different IP templates, and in case these projects are clustered into a single application, then applicants will be requested the Administrative and Legal documentation only once.