SDP Monitoring View - latest update: June 2026

The results of CP1 Monitoring are consolidated annually in the SDP Monitoring View.

Since its first edition, the yearly release of the SESAR Deployment Programme Monitoring View have represented the single point of truth for reporting the most detailed information on the status of the Common Projects, the cornerstone of SESAR Deployment in Europe since 2014, supporting the implementation of the European Air Traffic Management Master Plan.

This Report:

  • supports stakeholders in planning future investments and identifying risks or delays;

  • provides an integrated overview of ground and air-related implementation progress;

  • offers multiple perspectives on deployment status, including technological elements, stakeholder-specific progress and country-level details.

The SDP Monitoring View is organised into the following sections:

  • Section 1, which provides a high-level overview of the status of CP1 ground deployment in Europe. Specifically, it identifies all activities that have already been completed, those currently in progress and/or planned, as well as the implementation areas that have not been planned yet. On the basis of the inputs gathered during the Monitoring Exercise from the operational Stakeholders, this section also provides the overall roadmap towards full deployment, at Family, AF, and CP1 level, thus building a high-level plan to meet the Regulation deadline.

  • Section 2, which provides the full detailed picture of the implementation status of CP1 – clustered by SDP Family – in each airport or country, whilst also presenting a dedicated view per Stakeholder category for ground Stakeholders.

  • Section 3, which provides the outlook on CP1 deployment status for Airspace Users.

  • The document is finally complemented by a dedicated Appendix, which – building on the same input underpinning the view per Family and Services included in Section 2 – provides a view per Applicability Area, illustrating the status of the SDP Families and SWIM-based services within each country included in the geographical scope of CP1 Regulation and with regards to Network Manager and to Maastricht Upper Area Control Centre (MUAC). The Appendix also lists the relevant SDM-coordinated Implementation Projects contributing to move the deployment forward within each country.