    The tasks of the SESAR Deployment Manager are defined by Commission Implementing Regulation (EU) No 409/2013 article 9. In addition, as FPA coordinator, SDM is also the action coordinator for each (cluster of) implementation projects. As such, SDM will provide support and coordination services to the implementing partners in order to facilitate timely PCP implementation.